BMMI
Headquarters and Logistic Centre
Client: Bahrain
Maritime And Mercantile
Consulting Engineer: M.S.C.E.B.
Main Contractor: CEBARCO BAHRAIN SP
Location: Sitra, Bahrain
Contract Period: 18 Months
Contract Completion: December 1997
Value: US $ 5,810,000
Description:
The project involves the construction of a new head
office and logistics centre for a major supplier in the
FMCG market. The front section of the building houses the
corporate headquarters, compete with all office support
facilities from high density filing through to the
boardroom amenities.
The logistics centre is served by a multitude of
self-leveling loading docks that can cater for all sizes
of transportation. Extensive cold and cool rooms are
served by a dedicated refrigeration and control system,
the construction of which had to account for a high water
table and the possibility of ground freeze. Bulk dry
goods storage was provided by extensive vertical racking
which allows automatic replenishing of removed stock.
Externally extensive car parking, vehicle turning,
substations, gatehouses, fencing and all associated
infrastructure completes the bespoke facility.
|