North Manama Corridor Improvement Project
Client: Ministry
of Works and Housing
Consulting Engineer: Parsons Global Services
Main Contractor: CEBARCO BAHRAIN SP
Location: Manama - Seef Area
Contract Period: 24 Months
Contract Completion: In Progress
Value: US $ 26,000,000
Description:
Built in the most trafficked area in Bahrain the more
commonly know Seef flyovers is a unique project in
Bahrain. This is the first major grade separated
interchange to be constructed in Bahrain amongst and over
live traffic. Those who are familiar with Bahrain will
appreciate the severe traffic congestion in this area and
the monumental task that was undertaken to complete this
project.
The project comprises of five individual cast insitu box
girder post tensioned concrete bridges. Each bridge is
over 100m long in three spans with a maximum mid span of
50m. The bridge abutments are supported on piled
foundations located on the top of a massive sand
embankment. Also included in the project is the upgrading
over 3km of existing three lane dual carriageway and
introduction of three new on grade interchanges.
Notwithstanding the technical knowledge required for such
a unique project probably the greatest achievement has
been in the skills used to develop workable traffic
management programmes to ensure that this already
congested road continues to flow.
The project is on schedule to complete by May 2005. |